Georgia Power is taking 30 properties for a new transmission line. The family says it's for data centers. The utility says it isn't.
Ansley Brown posted a photo on Instagram of the power lines running behind the house she grew up in. Within months, Georgia Power had acquired that home as part of a 35-mile, 500-kilovolt transmission line that will take 30 residential properties across four Georgia counties. Brown said the takings were "for the data centers." Georgia Power said it is "not in the data center business."
The dispute is the story. It also names a portable question: when a utility takes homes for a grid upgrade, who is the line actually for, and can the answer be verified?
The Ashley Park–Wansley 500 kV Transmission Line Project runs from the Ashley Park Substation in Fayette County to Plant Wansley in Heard County, crossing through Fulton and Coweta Counties along the way. Georgia Power's own project page describes the line as part of broader transmission work needed for grid reliability, not as a feeder for any named data center campus. The utility will not say which specific new loads it expects the line to serve.
Fortune reported on July 26, 2026 that the Ashley Park–Wansley route is one slice of roughly 1,000 miles of grid expansion Georgia Power has on its planning map, with data centers cited as a major driver of regional load growth. Tom's Hardware and CBS News carried the same thread: 30 homes, one disputed justification.
The mechanism at work is end-use justification in transmission eminent domain. A utility can use eminent domain, the government's power to take private property for public use with compensation, to acquire property for a transmission line it has been authorized to build. The contested layer is the "for what." In state regulatory filings, that distinction shows up in the project justification, the cost allocation between ratepayer classes, and the load forecasts the utility submits. Georgia Power has not, in public filings tied to this line, named a specific data center customer.
The Brown family did not have to win the larger fight to get an outcome. After Rep. Brian Jack (R-GA) connected the family with Georgia Power leadership, the Browns settled with the utility for an undisclosed amount, according to Fortune's reporting. That is a small, real win: a congressional office intervening on one family's behalf, putting the contested-justification question on the political table rather than burying it in a rate case.
AP News reported in December 2025 that Georgia regulators had approved a major increase in electric generation capacity to serve data centers, supplying a separate regulatory backdrop. Reporting in the same chain also flagged an AI data center less than five miles from the Ashley Park Substation, accused of secretly drawing 29 million gallons of water. That 29-million-gallon figure is a single-source claim and has not been independently confirmed.
The pattern is not in doubt: utility-scale AI demand is changing how transmission projects get justified, routed, and contested, and it is doing so faster than the regulatory language for end-use disclosure is catching up. The 30 homes are a fact. The 35-mile line is a fact. The data-center justification is, for now, a contested attribution the reader can verify by reading Georgia Power's project filings and comparing them to the load forecasts the utility files in its next rate case, where state regulators review capital spending.